Pricing decisions

Review Material Costs Before You Honour a Quote

Find the material price change that would wipe out the contribution on an open quote.

Sources checked 3 min read

Separate what was promised from what was assumed

An estimator prepares a quote using a supplier price on Tuesday. By the time the customer decides, freight or material prices may have changed. Open quotes deserve a separate review because the work has been priced but the costs may not be locked in. The goal is to spot which quotes deserve a conversation before the business commits.

Open the estimate and highlight material lines that could move. Check whether supplier quotes are still valid, whether shipping is included and when goods can actually be delivered. If a price includes tax, confirm how you treated it in the estimate. Keep terms your customer already accepted separate from quotes still awaiting approval. If it is unclear what you agreed, check the contract before acting.

Key points

  • Update costs for quotes that are still open.
  • Review quote validity and buying dates before changing terms.
A selection of various tools scattered on a workbench in an industrial setting

Photo by Tima Miroshnichenko on Pexels

Find the room in the quote

Imagine a $12,000 quote with $6,000 in material, $3,400 in labour and $600 in other direct costs. The job is expected to contribute $2,000. A 15 percent increase in material adds $900 and brings expected contribution down to $1,100. If the owner needs at least $1,500 to help cover overhead, there is room for only $500 of extra direct cost under that original quote.

List the items that account for most of the gap. A different product might work if it meets the same specifications and the customer agrees. An earlier order may protect a price but tie up cash or create a storage problem. Changing only the freight route could be enough. Check each option for both cost and time instead of assuming all savings are equal.

Keep a simple register of open prices

A small business does not need a complicated system for this. Keep the quote number, expected customer decision date, supplier expiry date and material amount on one sheet. Review the ones with high material content first. Put a short note beside a fixed quote so nobody sends a different price without knowing the reason.

For new quotes, align validity dates where it makes sense and state what would require a new estimate. Give the customer a realistic time to decide. Confirm any provisional cost with the person responsible for purchasing, and record the lead time before you promise a start date.

Close the loop by checking what you actually paid against the estimate. When the same supplier charge surprises you twice, add it to the estimating checklist. The result should be a price your team can explain and a job your company can deliver profitably.

A question you may have

How often should I review outstanding estimates?

Start shortly before the supplier’s price expires or the customer is expected to decide. Look sooner when a major item has an uncertain lead time. Keep a record of commitments you already made so an updated purchasing assumption does not automatically change what your customer owes.

Official sources

  1. BDC definition of direct costs
  2. BDC guide to testing financial assumptions
  3. BCcampus guide to purchasing

Talk with HBT Accounting

Meet Husain Haroun, CPA

Call or email and we will tell you which records we need and what the work costs, in writing, before anything starts.

Important. This article provides general educational information, not legal or tax advice for a specific business. Rules, administrative policies, rates and deadlines can change. Confirm your facts and current obligations with the responsible government agency and a qualified adviser.